News
| Installation of a Steam/hot water boiler plant with a capacity of 1,2 MW located in Serpukhov district is completed. Installation of a commercial natural gas flow rate measuring station located in Serpukhov district is initiated. |
| A block-modular boiler house with a capacity of 2.0 MW intended for heat supply of a industrial facility in Norofominsk district has been put into operation. Installation of a Steam/hot water boiler plant with a capacity of 1,2 MW located in Serpukhov district is initiated. |
| A block-modular boiler house with a capacity of 2.0 MW in Podolsk district has been put into operation. Installation of a hot water boiler plant with a capacity of 2,0 MW located in Serpukhov district is completed. |
| Erection of high-pressure gas pipeline 400 meters long is completed in Serpukhov district. |
| The assembly of a hot-water boiler with a capacity of 2.0 MW in Serpukhov district has started. |
| The designing process of the gas supply system in Serpukhov district has started. |
| The designing of the hot-water boiler with a capacity of 2.0 MW in Serpukhov district has started. |
| A chimney (H = 20m, 2x500mm) with flues fastened on the base plate, has been manufactured and assembled. |