January 2015, Two 30 m high steel chimneys are erected in Dmitrov district. |
December 2014. Serpuhov district. Installation of steam and hot water boiler house with total capacity 7,06 Gkal/h is completed. |
December 2014, delivery of 32 chimneys for objects in various regions of the Russian Federation is completed. |
November, 2014, Serpuhov district. Installation of hot oil boiler house with total capacity 1,0 MW is completed. |
August 2014. Installation of steam and hot water boiler house with total capacity 7,06 Gkal/h started in Serpuhov district |
June 2014, We started manufacturing of 30 m high steel chimney for power plant in Rostov. |
May 2014, A 30 m high steel chimney is erected in Obolensk. |
April 2014, A 55 m high steel chimney is erected in Voronezh. |